We plan, design and deliver quality designs with exceptional engineering concepts. we meet each and every demand of our clients considering the project specification. We rely on the main consultant standards while considering the demand set forth by each of client contractors.
Contractor: Al Futtaim Construction LLC./EFECO Consultant: SSHIC INTERNATIONAL
ENGINEERING CONSULTANT
Client: EMAAR- The Lagoons Phase One LLC.
Scope of Work
•Flexibility evaluation of chilled water pipes as per ASME B 31.1
•Finite Element Analysis of Riser Anchor Support for CHW Pipes
Contractor: ALEC Engineering & Contracting L.L.C
Consultant: WSP
Client: EXPO 2020
Scope of Work
• STRUCTURAL VALIDATION OF SKYLIGHT RAHU`S, RAMP RAHU`S & TSF
• STRUCTURAL VALIDATION OF SECONDARY SUPPOPRTS
• Flexibility evaluation of chilled water pipes as per ASME B 31.1
• Pipe Support Evaluation and sizing.
Contractor: Al-Futtaim / Carillion/Voltas
Consultant: WSP/Hopkins Architect Dubai
Client: Dubai World Trade Centre
Scope of Work
• The scope includes the flexibility analysis of complete chilled water (Supply & Return) pipes lines of C1, C2 and C4 building, including the ETS room.
• Detailed project report with modelling details, input parameters, description of worst case scenarios, Stress Isometric drawing, Restraint summary, displacement reports etc.
Contractor: Nurol LLC/Trinity Engineering Services LLC
Consultant: NORR Architects & Engineers
Client: THE LAGOONS PHASE ONE - L.L.C
Scope of Work
•Flexibility evaluation of chilled water pipes as per ASME B 31.1
•API Pump Calculations
•Support Structural Calculations
SHAMS ABU DHABI
Contractor: Construction General Contracting House Ltd./MAPCO L.L.C.
Consultant: AECOM MIDDLE EAST LIMITED
Client: ALDAR PROPERTIES PJSC
Scope of Work
•Flexibility evaluation of chilled water piping network as per ASME B 31.1
•API Pump Calculations
•Support Structural Calculations & Evaluation
Contractor: CHINA STATE CONSTRUCTION ENGRG. CORP (MIDDLE EAST) (L.L.C.)
Consultant: ARCHGROUP
Client: EMAAR PROPERTIES CO. P.J.S.C.
Scope of Work
•Flexibility evaluation of chilled water piping network as per ASME B 31.1
•API Pump Calculations
•Support Structural Calculations & Evaluation
Client: DUQM REFINERY & PETROCHEMICAL INDUSTRIES
Supplier Name: SKM AIR CONDITIOING LLC
Project No: JI-2037/SO0267
Project Location: Oman
Scope of Work:
The Dynamic study of Air conditioning equipment is conducted to qualify Equipment by analysis. The purpose is to establish the Seismic Capacity of the Equipment so that the equipment is operable after a seismic event and maintains structural integrity.
Client: DUBAI COMMERCITY
Project Details: P42 - UMM RAMOOL DEVELOPMENT UMM RAMOOL DUBAI.
Project No: 5502
Lead Consultant: P&T Architects and Engineers Ltd.
Main Contractor: International Electro-Mechanical Services Co. (L.L.C.)
Scope of Work:
• Seismic stress analysis of chilled water piping network as per ASME B 31.1
• API Pump Calculations
• Support Structural Calculations & Evaluation.
Client: MIRAL
Project Manager: EllisDon
Project No: C2
Consultant: GAJ Middle East
Main Contractor: Shapoorji Pallonji Mideast L.L.C
Scope of Work:
• Seismic study of the FIRE FIGHTING PIPES, SMOKE EXTRACT & PRESSURIZATION DUCT & CABLE TRAY as per ASCE-07 and to define lateral /Longitudinal bracing as per seismic lateral loads.
Client: Al tayer
Main Developer: REEM Developers
Project Consultant : APG
Main Contractor : Al FARA`A
Sub-Contractor : SEMCO
Project Location: MIXED USE DEVELOPMENT IN RAWDHAT - Abu Dhabi
Scope of Work:
Acoustic/Vibration study is carried out for AHUs, FAHUs, CHILLERS, FCUs, CHILLED WATER PUMP and FANS
Site/Location details : PROPOSED BUILDING (G + 5P + H.C + 43 TYPICAL + 1 SERVICE + ROOF)- AL MAMZAR, SHARJAH-UAE
Client : SHEIKH MOHAMMED BIN ABDULLAH ALQASMY
Consultant : SHARJAH ENGINEERING CONSULTANTS
Main Contractor : Al MAWARID GENERAL CONTRACTING
Sub-Contractor : AL MAWARID ELECTROMECHANIC LLC.
Scope of Work:
Acoustic/Vibration study is carried out for AHUs and FAHUs
Site/Project details : P42 - UMM RAMOOL DEVELOPMENT UMM RAMOOL DUBAI. CENTRAL UTILITY
Project Number : 5502
Client : DUBAI COMMERCITY
Lead Consultant : P&T Architects and Engineers Ltd.
Main Contractor : International Electro-Mechanical Services Co. (L.L.C.)
Scope of Work:
Surge and Hydraulic Analysis study of District Cooling Network using AFT package.
Project: THE ADDRESS RESIDENCES DUBAI OPERA
A2 / A3
Client: EMAAR PROPERTIES - PJSC
Lead Consultant : KHATIB & ALAMI
Main Contractor: TAV TEPE AKFEN INVESMENT CONSTRUCTION & OPERATION.
Sub Contractor: EFECO L.L.C
Scope of Work:
Surge Analysis study of Water Supply Lines and Gravity feed lines.
Project Number: J-166
Client : AL SHAIKHA RODHA BENT AHMED BIN JUMA AL MAKTOUM
Lead Consultant : ALHASHEMI
MEP. Consultant : GCE CONSULTANTS
Main Contractor : AL MALIK BUILDING CONT. CO. LLC
Sub Contractor : SAIFCO Electromechanical Works (LLC)
Scope of Work:
To study primarily the pressure distribution in the piping and the requirement of PRV station in floor branch piping of G+3 EMIRATES HOSPITAL QUSAIS BR. & G+5 PARKING BUILDING Project.
Project Number : C2
Client : MIRAL
Project Manager : EllisDon
Consultant : GAJ Middle East
Main Contractor : Shapoorji Pallonji Mideast L.L.C
Scope of Work:
The frame work consists of 28 no’s individual cassettes accommodating several MEP and allied utility lines, tracks, pipes etc. and the evaluation shall adhere to applicable design codes and standards to deduce the performance of the proposed structural framework.
Site/Location details : MOBILITY SIGNATURE PAVILION
Client : EXPO 2020
Local Consultant : WSP
Main/MEP Contractor : ALEC Engineering & Contracting L.L.C
Scope of Work:
· Modelling and FE Analysis of Secondary Beam, Drop Down Columns, and mounting frame.
· Structural Analysis (FEA) of support to validate for structural integrity against dead loads applicable.
Site/Location details : MOBILITY SIGNATURE PAVILION
Client : EXPO 2020
Local Consultant : WSP
Main/MEP Contractor : ALEC Engineering & Contracting L.L.C
Scope of Work:
Finite Element Analysis (FEA) of structure to validate for structural integrity against applicable loads for Deck slab structure.
Contractor: Meydan Sobha.
Consultant: Ae7
Client: Emaar
Scope of Work:
To examine the designed ventilation system for the car
parking area in the “Meydan One mall, Basement 1 using CFD. To simulate the ducted extract system and makeup air. The simulations are carried out to study the system requirements on basis of safety regulations and standards pertaining to Dubai civil defense. And also to check whether it meets the sufficient visibilities & temperatures in case of fire.
Contractor: Meydan Sobha.
Consultant: Ae7
Client: Emaar
Scope of Work:
• Carbon Monoxide Simulation carried out Following two references suggest that PPM level should be maintained at or below 30-35ppm.
• Abu Dhabi Occupational Safety and Health System Framework, Occupational Standards and Guideline Values (July 2016).
• AESG, Ambient Outdoor Air quality Standards in UAE
Contractor: Meydan Sobha.
Consultant: Ae7
Client: Emaar
Scope of Work:
• Each of 9 vehicles (out of maximum 187 cars, 5% cars are chosen) emitting 46.25mg/s à (reference: ASHRAE Handbook).
• Jet fans operating at maximum capacity.